Units 1, 1a, 2, 3, 3a, 4, 4a, 4b, 4c, 4d, 5b Wellesbourne Distribution Park

Returning for Phase 3 within this Industrial Park on behalf of Barwood Developments, the works involved the demolition to top of ground bearing slab of units 1-5b and also consisted of the removal of all soft strip and asbestos in accordance with the pre-demolition surveys. All demolition materials except for the crushed concrete and masonry were removed from site. Crushed demolition arisings were stockpiled in areas agreed with the client team on original hardstands.

 Surrounding the site were various live industrial buildings, and our works were undertaken in consideration of this. Water supply to a neighbouring car wash facility was fed through our site and maintained throughout the course of our works.

 As park of our works we removed three external fuel tanks which were drained and cleaned by suitable subcontractors to allow for cold cutting and disposal by our trained operatives.

 

 

Location:

Wellsbournce, Warwickshire

Client:

Barwood Developments

Project Value:

£147,000

Considerate Constructors National Site Awards 2014 - Bronze Award Winner

We are delighted to announce that following our recent nomination for a prestigious National Site Award we were successful in our endeavours picking up a Bronze award at the Ceremony held in London on 3rd April.

Full Story >

H Smith (Engineers) Wins another National Considerate Constructors Award

It is our pleasure to announce that we are yet again winners at The National Considerate Constructors Awards, this year to be held at Plaisterers' Hall on the 3rd April 2014.

Full Story >

Clients

Staff Login





Forget Your Password?